Liquidated Damages

A contractual provision specifying the amount of damages payable on breach, fixed in advance by the parties' agreement. Replaces common-law actual-damages calculation with a predetermined amount, providing certainty and avoiding the cost of proving actual damages.

A liquidated damages clause is a contractual provision specifying the amount of damages payable on breach, fixed in advance by the parties' agreement. Liquidated damages clauses replace common-law actual-damages calculation with a predetermined amount, providing certainty and avoiding the cost and difficulty of proving actual damages.

Validity test (Phillips two-part test)

A liquidated damages clause is enforceable in Texas only if (1) the harm caused by the breach is incapable or difficult of estimation at the time of contract; and (2) the amount of liquidated damages is a reasonable forecast of just compensation. If either prong fails, the clause is an unenforceable "penalty" rather than valid liquidated damages.

Distinction from penalty

Texas courts disfavor penalty clauses, provisions designed to punish breach rather than compensate the non-breaching party. Excessive amounts disproportionate to anticipated harm, or lump-sum amounts triggered by any breach regardless of materiality, are commonly held unenforceable as penalties.

UCC sales (§ 2.718)

UCC Article 2 codifies the common-law approach: liquidated damages must be reasonable in light of (1) the anticipated or actual harm caused by the breach; (2) the difficulties of proof of loss; and (3) the inconvenience or non-feasibility of otherwise obtaining an adequate remedy. Unreasonably large amounts are void as a penalty.

Practical context

Liquidated damages provisions are common in construction contracts (delay damages), real estate (earnest money), employment (training repayment), and intellectual property licenses. Drafting failures involve setting amounts that bear no realistic relationship to anticipated harm. Sophisticated drafting includes brief recitations of the parties' difficulty estimating actual damages and the reasonableness of the liquidated amount.

Companion article: Contract Disputes in Texas

Practice guide: Breach of Contract in Texas

Related Terms
Sale of Goods· Statute of Frauds
Referenced by
Consideration· Construction Contract· Earnest Money· Limitation of Liability Clause· Pay-When-Paid vs. Pay-If-Paid
Last updated: September 28, 2026